University Medical System | Multiple Projects

Lubbock, TX

About the project

Since 1988, Lee Lewis Construction, Inc. has worked with the University Medical Center steadily to complete numerous projects on various campuses. Projects include:

 

  • GI Center
  • East Tower
  • Parking Structure
  • 5th & 6th Floor Expansion
  • Medical Office Plaza II
  • Outpatient Pavilion Expansion and Medical Office Building
  • Southwest Cancer Center Expansion (2004)
  • Emergency Room / Radiology Expansion
  • OR Renovations
  • Lubbock General Hospital O.P. Surgery & O.B.
  • 6th Floor Finish Out
  • Medical Office Plaza I
  • Power Generator Facility Southwest Cancer Center (1994)
  • Medical Office Plaza II – 2nd Floor Finish Out
  • Pediatrics Hospital
  • Orchard Park Clinic
  • PNS Family Physician Clinic Radiology Expansion
  • PNS Family Care Clinic
  • Medical Office Plaza II – 1st Floor Finish Out
  • Southwest Cancer Center Expansion (2009)
  • ER Fast Track Expansion University Medical Center (Original Hospital)
  • Administration Renovations Cath Lab Renovations
 
 
 
 
 
 
 

 

Project Overview

Owner

University Medical Center

Architect

Parkhill, BGR, Condray, FBT & HDR

Project Delivery

CM@Risk & CSP

Project Details

Addition and Renovation
SF Varies Per Project